PROJECT TIMELINE

 

 

 

 

 

 

START-UP DATES

Design Review Submittal . .February 2000
Design Review Approval . July 2000
Commencement of Demolition Work . April 2000
Commencement of Construction . November 2000
.

COMPLETION DATES

Block 1 - Renovation . Completed March 2002
Block 2 . Completed November 2002
Block 3 - Renovation . Completion Estimated Fall 2006
Block 3 - The Henry . Completed May 2004
Block 4 - New Construction . Completed May 2003
Block 5 - The Louisa
. Completed April 2005